Sl#
|
Leasee Name
|
Status
|
Action By
|
Action Date
|
Remarks
|
1
|
MCL
|
working
|
----
|
3/31/2011 12:00:00 AM
|
----
|
2
|
MCL
|
suspended
|
DDM
|
8/31/2012 12:00:00 AM
|
Suspension of Mines for want of statutory clearence.
|
3
|
MCL
|
Revoked
|
----
|
9/26/2012 12:00:00 AM
|
As per the order of Hon'ble Supreme Court of India dt 21.9.2012 carry on mining operation for a period of two month from the date of issue of order 21.9.2012.
|
4
|
MCL
|
suspended
|
DDM
|
11/21/2012 12:00:00 AM
|
Suspension of Mines for want of statutory clearence.
|
5
|
MCL
|
Revoked
|
----
|
12/7/2012 12:00:00 AM
|
Hon'ble Supreme Court allowed to normal despatch of coal to destination from the date of hearing i.e dt-7/12/2012 to upto 4/1/2013(25 days)
|
6
|
MCL
|
working
|
----
|
4/3/2022 4:02:40 PM
|
Working as per DM(O) letter No.2777/DM.,Dt.02.04.2022.
|